On September 26, the Kharkiv Regional State Administration's Capital Construction Department announced an open tender for the construction of an oncology center with an expected cost of UAH 3,16 billion. Are there any other problems in Kharkiv?

Project visualization. FB/Kharkiv Region Medicine
This was reported in the Prozorro system , writes Anna Soroka, Nashi Groshi.
In August, the Department awarded the Academy Research and Production Design Enterprise LLC a non-bid contract to revise the design for the first phase of construction of the Regional Oncology Center complex at 4 Lesoparkivska Street in Kharkiv for UAH 43,22 million. Now, a tender has been announced for the work, which the winner will be required to complete by the end of 2028.
The procurement plan states that it is being financed through the local budget under the classification "Implementation of public investment projects in the healthcare sector." The tender documentation also notes that "The procurement is being carried out within the framework of the Ukraine Facility . "
The client will be able to pay the contractor an advance payment based on an invoice for the organization of work and the procurement of materials, amounting to no more than 30% of the annual work volume. The advance payment will be made within one month of the invoice date and must be used within one year of receipt. Final payments will be made within three months of the completion and acceptance of all work specified in the future contract.
Construction of the oncology center began in 2019 and was halted just before the invasion. This photo shows the facility's condition at the time:


The first phase involves completing the first section of the treatment and diagnostic building (surgical, admission and diagnostic departments, and clinical research department), the power unit (gas boiler house, chiller room, and central heating station), a therapeutic gas station, and two transformer substations, as well as the installation of a civil defense shelter. The shelter, with its underground passage, is designed to accommodate 1100 people.
The technical specifications for the work included medical equipment, including an Optima 520 P-58 CT scanner, a Medray Max DR Z-17 digital X-ray diagnostic stationary device, and four Hamilton-C3 O-191 artificial lung ventilation devices.
To participate in the tender, you must submit three similar contracts, comparable in scope and nature of work. These contracts must be performed at facilities with a CC2/CC3 impact class, at least one of which is a healthcare facility and at least one with a CC3 impact class.
It is also mandatory to have a chief engineer, a foreman, an occupational safety engineer, and at least three site foremen with a higher education and at least ten years of experience.
Subscribe to our X channel , Telegram channel and Facebook page!
Stay informed about who is doing business, in politics, and supporting corruption in Ukraine!
In addition, to confirm the financial capacity of the participant, the average annual turnover over the last four years must be at least 10% of the price of its tender offer.
It is also necessary to confirm the availability of the equipment and material resources necessary to perform the work covered by the procurement. However, there are no specific requirements.
The security for the execution of the contract in the form of a bank guarantee amounts to 0,5% of its price.
Requests for clarification and appeals against the procurement terms will be open until October 9, and tender proposals can be submitted until October 12. The auction is scheduled for October 13.
History of the Kharkiv Oncology Center
As a reminder, construction of this oncology center in Kharkiv began back in 2019, based on a design by Kharkivproekt Institute LLC. At that time, the construction contracts were won by Trest Zhilstroy-1. In 2020-2021, contracts with it were terminated due to the need to adjust the design, with UAH 57,25 million in payments. In 2020, Romb+ became the contractor . In 2021, the facility was included in Volodymyr Zelenskyy's "Great Construction" program . This year, the Romb Inc. Consortium won the new tender. Following Russia's full-scale invasion, contracts with both contractors were terminated in 2022: Romb+'s was terminated due to the contractor's failure to fulfill its contractual obligations, with payment of UAH 157,82 million, and Romb Inc's was terminated by mutual agreement, with zero payment.
In January 2025, the newspaper "Public. Kharkiv" quoted the head of the Kharkiv OVA, Oleg Sinegubov:
"The Ministry of Health has already allocated 50 million hryvnias for this year. We will complete the project adjustments using funds from the regional budget, which is approximately 24 million hryvnias, because the project is large-scale, costing over 1.5 billion hryvnias. These first 50 million hryvnias are for resuming construction. And we have an agreement with the ministry that we won't limit ourselves to this 50 million hryvnias. The contractors will do as much as they can."
In August , it turned out that 50 million UAH would only be enough to adjust the first stage of the project.